Aggregate Industries was recently chosen to help restore the ‘world’s first skyscraper’, the grade 1 listed Main Mill at Shrewsbury Flaxmill Maltings in Shropshire.
The site comprises of eight listed buildings, including the Main Mill, which was built in 1797. As the first iron-framed building, the site paved the way for modern skyscrapers
Originally, it was a steam-powered flaxmill spinning linen thread from flax, before being converted into a maltings at the turn of the 19th century, but has now been derelict for decades.
The site was recently purchased by Historic England as part of an initiative to save and restore it along with Shropshire Council and the Friends of the Flaxmill Maltings, a visitor centre opened in 2015 as part of the first phase of restoration works. Now in its second phase thanks to a Heritage Fund grant, work is currently in progress to fully restore the Main Mill and Kiln buildings.
When complete in 2021 these buildings will be home to a brand new public interpretation space and café at ground level and several thousand feet of contemporary office and meeting space on the floors above, creating a new learning and enterprise quarter for the region.
A key requirement of the project was to source an aggregate solution that would be lightweight enough not to overload the fragile iron structure. Therefore, main contractor Croft Building and Conservation Ltd chose Aggregate Industries, who worked with partners SMC Minimix Concrete, to supply its revolutionary Lytag lightweight secondary aggregate in order to support the fragile iron structure of the building during its redevelopment.
Lytag was ideal, as it can effectively reduce the composite deck concrete slab load by approximately 25% over normal weight control, while offering the same level structural performance. Made from secondary aggregate, Lytag also offers a much more environmentally friendly alternative to standard concrete, as thanks to its unique properties, it can help to significantly reduce the amount of material required on a project, along with the associated carbon emission produced in delivery.
Barry Mellor, Commercial and Technical Manager for Lytag, comments: “[Croft Building and Conservation] had been struggling to find a concrete supplier due to specific quantities being no more than 24 cubic metres, so we partnered with SMC Minimix Concrete, as they were ideally placed to deliver the volume required. We worked closely with the team to facilitate the project, sharing advice and mix designs for the end product, in order to provide a holistic solution for the customer that played to each of our strengths; product innovation and logistics.
“The material was delivered by SMC and pumped by Pez Concrete Pumping, firstly to the fifth floor, followed by the fourth and finally the third floor; all within four hours, which was even more impressive due to the pump operator having to dismantle and set up for each floor pour. Product segregation can be a problem on these types of jobs, especially with the pumping height being 22m, due to potential increased pump friction causing excess vibration and the risk of blockages, however placement went as expected and the result was a perfect finish.”
Visit the Aggregate Industries website
Paris balconies, with their timeless charm and practicality, are becoming something of an architectural staple in urban and rural environments, as CRL explains here…
Posted in Articles, Balustrades and Guardrails, Building Industry News, Building Products & Structures, Case Studies, Garden, Glass, Glass Projects, Restoration & Refurbishment, Retrofit & RenovationEnglish Spirit Distillery has used an extensive package of Altro products front and back of house, in their new visitor centre café, shop and viewing area for the working distillery.
Posted in Articles, Bathrooms, Bedrooms & Washrooms, Building Industry News, Building Products & Structures, Building Systems, Case Studies, Floors, Interior Design & Construction, Interiors, Kitchens, Restoration & Refurbishment, Retrofit & Renovation, Timber Buildings and Timber Products, WallsAbloy UK has supplied The Safety Letterbox Company Ltd with a bespoke Sentry CL811 Camlock for use in its Secure Information Boxes, assisting life safety and complying with new regulations and legislation for high rise buildings.
Posted in Access Control & Door Entry Systems, Architectural Ironmongery, Articles, Building Industry News, Building Products & Structures, Building Regulations & Accreditations, Building Services, Case Studies, Facility Management & Building Services, Health & Safety, Posts, Restoration & Refurbishment, Retrofit & Renovation, Security and Fire ProtectionSituated at the northern edge of a newly developed retail park near Bristol, the Abbey Wood Travelodge was conceived as part of the company’s new Budget-Luxe line of hotels – it features CUPACLAD, from CUPA PIZARRAS.
Posted in Articles, Building Industry News, Building Products & Structures, Building Systems, Case Studies, Cladding, Concrete, Cement, Admixtures, Facades, Posts, Restoration & Refurbishment, Retrofit & Renovation, Walls