The Future Homes Standard has brought about the review of all aspects of residential building design. Here, GDHV outline the changes to Part F of the Building Regulations which address ventilation and maintenance of indoor air quality in residential dwellings.
The aim behind the update to Part F was to simplify ventilation requirements whilst aligning air tightness and system specification.
This was following a government review of ventilation and indoor air quality in new homes. This showed only three of the eighty homes monitored complied with the current standards for Part F: Ventilation, in part due to complexities within the regulation itself.
The Government began by proposing that the four system types, as listed in the current Part F, are updated.
Guidance has been removed for passive stack ventilation, formerly System 2 and the remaining three systems have been renamed and guidance given on aligning these with the most suitable level of air tightness.
The aim of this is to provide more support for designers in specifying the best solution for their project based on air permeability levels.
System Type |
Dwelling covered by proposed guidance changes |
Natural ventilation (formerly System 1) |
A design air permeability higher than 5m3/(h.m2) at 50 Pa; Or An as-built air permeability of higher than 3m3/(h.m2) at 50 Pa
|
Continuous mechanical extract ventilation (formerly System 3) |
Any level of airtightness |
Continuous mechanical supply and extract ventilation (formerly System 4) |
Any level of airtightness (although MHVR efficiency will improve with increased airtightness)
|
When this becomes legally enforceable (expected June 2022), designers will need to seek expert advice if using a system type in a dwelling different to the above. However, SAP credits may be limited where this is the case.
In a move to make compliant design easier, the revised Part F will also change the way whole dwelling ventilation rates are calculated. This will mean designers won’t have to estimate the number of people in bedrooms by changing to a constant factor.
For more about the Part F changes and the impact this could have on residential ventilation, request GDHV’s Future Homes Standard CPD online.
Alternatively, to learn more about our services with ventilation specification and design, visit our dedicated mechanical ventilation page.
Geberit is introducing a new concept which allows end users to combine basins and furniture across its Aspire range for the first time
Posted in Articles, Bathrooms & Toilets, Bathrooms, Bedrooms & Washrooms, PostsDiamond drilling specialist Castle & Pryor was recently tasked to make a storage warehouse into one open space, removing the central dividing wall and levelling the floor
Posted in Articles, Plant, Equipment and Hire, Posts, Restoration & Refurbishment, Retrofit & Renovation, Site PreparationFollowing reports of power outages at a UK airport, Abloy UK is flagging-up the need for effective access control solutions that maintain security even when the power supply is disrupted
Posted in Access Control & Door Entry Systems, Articles, Posts, Security and Fire ProtectionVent-Axia has supplied its CIBSE award winning Sentinel Apex for the ventilation of ECO MEP’s highly-efficient commercial office environment in Ashford, Kent
Posted in Air Conditioning, Articles, Heating, Ventilation and Air Conditioning - HVAC, Posts