It may be last orders for some great British pubs, but for others its discovering exciting ways of transforming commercial structures into luxury residential dwellings, as Delta Membranes explains here.  

Delta Registered Installers, Advance Property Preservation Ltd, were engaged to assist on a troublesome vaulted basement to a property, based in central London, which had already been converted into high living accommodation.   

Just off the basement area were two large vaults around 12m long.  Made from brick barrel construction, this below ground space had previously used for storing kegs of ale.

One of these vaults had previously been converted into a spa area with jacuzzi and steam room, with the other used as a storage area.  The owners had previously had the storeroom tanked with a Type A, render system, but this approach repeatedly failed, allowing for substantial water ingress, which was causing damage to items stored in this area.

With Structural Waterproofing, one of the major contributors to project failure lies with the design. When hiring contractors, ensure the design, procurement of materials and installation is undertaken by one specialist will naturally reduce these known and associated risks. 

A specialist contractor will always be able to offer quality assurances.

Delta Membranes

 

Methodology 

Consideration to the grading of the structure (habitable requirements in this instance) is key to specifying an appropriate waterproofing system. 

For Grade 3 Habitable environments, two systems of waterproofing may be required.

For Grade 2, Habitable environments, only one form of waterproofing may be required, but caution should be applied because different stored items require very precise environments.

Prior to any product specifications, Advance Property Preservation Ltd firstly undertook thorough site investigations.  This initial investigation allows for important ‘cross-checks’ to ensure any proposals will meet not only customer requirements but will also conform to BS 8102:2009, the British Standard which governs the waterproofing industry.

On surveying the site, which was directly below a road, it was evident vibration from traffic was causing the existing render system to crack, which was resulting in frequent water ingress.

Delta Membranes

Advance Property Preservation Ltd proposed installing the Delta Type C Cavity Drainage System along with mechanical ventilation.  The Delta Type C Cavity Drainage System allows for slight movement and vibration, without altering the dynamics of a structure.    

In principle, a Cavity Drainage System allows for moisture or running water to travel behind the membrane in a controlled drainage system, whilst requiring minimal preparation and disturbance to an existing substrate.

Delta MS 500 was installed to walls and barrelled ceilings, with Delta MS20 loose laid and joined to the MS 500 wall membrane laid to the floor, with a protective screed subsequently poured on top. 

Below the floor membrane, perimeter drainage channels were sited within rebates, allowing for suitable drainage of any future water ingress and being diverted to suitable discharge points.

It seems natural to focus on the installation itself – Advance Property Preservation also considered the final operation, ensuring the Type C System was serviceable and that future and ongoing maintenance was possible. 

After the Type C System was installed, walls and soffits were battened and boarded with moisture resistant plasterboard and plastered over.  Once complete, the walls were painted with an anti-mould paint, with insulation and timber oak flooring then being laid.

A moisture sensitive, humidistat-controlled fan was fitted, as well as new lighting to give the client a new dry storage space.

Case Study Results

The clients were delighted with Advance’s approach. Any structural waterproofing is a technical and design driven approach. Because the customers engaged with Delta Registered Installers, Advance Property Preservation Ltd were able to sequence the works in three weeks! 

Key matters which significantly impact the efficiency of the site installation were immediately identified in the initial site inspection, allowing for a suitable solution to be created.

Delta Membrane Systems,
Delta House,
Merlin Way,
North Weald,
Epping,
Essex,
CM16 6HR
United Kingdom

Visit Delta Membrane Systems' website

Leave a Reply

Latest news

Reynaers

Reynaers broadens Vision 7 functionality with new panic hardware

Reynaers Aluminium has added new panic hardware options to its Vision 7 Thermal Commercial Door – introducing both surface mounted and concealed systems for ease of opening in the event of an emergency.

Posted in Access Control & Door Entry Systems, Aluminium Products, Architectural Ironmongery, Articles, Building Industry News, Building Products & Structures, Building Services, Building Systems, Doors, Facility Management & Building Services, Health & Safety, Innovations & New Products, Restoration & Refurbishment, Retrofit & Renovation, Security and Fire Protection

Geberit
ASSA ABLOY
Mitsubishi Electric

Filton and Bradley Stoke MP visits Mitsubishi Electric installation

Claire Hazelgrove, Member of Parliament for the Filton and Bradley Stoke constituency, visited Brabazon on 7 November to see firsthand the installation of innovative Ecodan heat pumps by Mitsubishi Electric.

Posted in Articles, Building Industry News, Building Products & Structures, Building Services, Case Studies, Facility Management & Building Services, Heating Systems, Controls and Management, Heating, Ventilation and Air Conditioning - HVAC, news, Pipes & Fittings, Plumbing, Retrofit & Renovation, Sustainability & Energy Efficiency