DensDeck® Prime Roof Boards were specified as cover boards for the steel deck flat roof build-up of the mission critical Amazon data centre in Zaragoza. The specification of DensDeck® Prime Roof Boards is aimed at increasing the durability, puncture resistance, and fire resistance of the data centre flat roof build-up.
The Amazon data centre in Zaragoza is part of a three data centre development in the Aragon region. This is planned to become the first dedicated zone of data centres in Spain for the US based company. Ingennus Urban Consulting SLP and Arup Group Limited planned and designed the project. The work on site commenced in December 2020, and the data centre was ready for operations in May 2021.
The original specification of roof cover boards for this project was changed from cementitious boards early on. Jesús Huerta, Specification Manager for BMI Iberia, oversaw the new specification for the roofing system plans.
He explains: “The key drivers for the cover board selection were fire and puncture resistance and Factory Mutual (FM) approval for the whole roof assembly. The change was rooted in the considerable cost savings that could be achieved with DensDeck® Prime Roof Boards (a glass mat gypsum based board) compared to the original cementitious cover boards by a competitor. We achieved a reduction of over €3 per square meter.”
Businesses and critical infrastructure worldwide depend on data centres’ secure and round-the-clock operation. Any downtime can be costly to the data centre, and the operations contingent on the data centre providing uninterrupted service.
Emerson Network Power study estimated the average total cost of outage per minute at $7,918 in 2016 (approximately €7,355). Reducing the risk of operational downtime and expediting project delivery is critical for any data centre project.
The roof assemblies of the three Amazon Zaragoza buildings span over 40,000 m2. The roof systems consist of steel decks, BMI self-adhesive vapour barriers, Hardrock 391 stone wool panels overlaid with cover boards. These are mechanically fixed BMI TPO single ply membranes. The cover boards were therefore installed over the insulation layer and below the single ply membrane.
DensDeck® Prime Roof Boards are compatible with the installed BMI membrane. The cover boards created a flat, firm substrate to aid the mechanical fixings. This helps protect the membrane from puncture and the insulation boards from damage. The roof of the Amazon Zaragoza data centre houses a large amount of heating, cooling, and air conditioning technology.
The installation of the heavy plan, such as MVHR, and other heating, cooling, ventilation and air conditioning equipment, and the need for frequent, regular maintenance warranted that every effort was made to offer extra protection for the roofing membrane.
Both gypsum and fibreglass, used to manufacture DensDeck® Prime Roof Boards, are classified as non-combustible materials as described and tested by ASTM E136. The cover boards are also included in over 180,000 roofing assemblies with a Factory Mutual (FM) Class 1 fire rating.
The glass mat-faced gypsum core boards help increase the fire resistance of the roof assembly from external fire sources when installed as a cover board. This is key for the Amazon Zaragoza data centre roof with many electrified HVAC systems, plant, and technologies.
Incidentally, the cover boards also help protect the membrane from externally transferred fire sources, such as embers, that can often be carried by wind and cause unexpected fires.
Jesús explains what certification he looks for when specifying coverboards: “There are certifications that I often prerequisite for a project; UL Class A1, BRoofT1 and Bs1-d0 as per BS-EN 13501-1. The FM 4470 is now a standard requirement for many clients.”
FM Approval is one of the main specification drivers in the US. Each building product that passes the five-step approval process is issued with an FM mark to support property loss prevention and signify that FM believes the products will perform as expected.
FM has their own fire performance testing, and this is extraordinarily stringent. European designers, specifiers and installers are increasingly leaning on FM Approval when selecting roof build-ups.
Jesús continues: “Due to the cost implications of any unexpected roof maintenance, the client was looking for building materials capable of delivering something that would correspond to the well-known warranty known in the US as NDL – No Dollar Limit.
“This means that the warranty covers the cost of any repairs, regardless of the cost. We at BMI offered our Solution Guarantee, which matched the NDL. However, the FM Approval of the roof system was critical for the specification.”
The concept of FM Approval is concerned with property protection and property loss prevention. The FM Approval strategy is based on collected data of actual losses incurred over the years. This set the development of over 200 approval standards. Specifying a product such as DensDeck® Prime Roof Boards, a product with FM credentials available for a significant number of installations across flat and low slopes roofs, offered the client extra assurance of quality and durability.
We asked Jesús what he thinks about DensDeck® Prime Roof Boards: “In my opinion, they are a building element that offers the opportunity to improve the quality of construction and improve technical figures and performance of our (BMI) roofing systems.”
Contact the company for more information on DensDeck® Roof Boards and DensDeck® Prime Roof Boards. It is happy to discuss how its range of roof and cover boards can help achieve specific performance requirements and speed up the installation of your low slope commercial roof system.
CONTACT: densdeck.buildgp.com/contact-us
EMAIL: [email protected]
Fire-resistant DensDeck® Roof Boards are helping to increase the performance of the solar panel flat roof system of IKEA Bangalore. Click the link for more info.
Georgia-Pacific Building Products
133 Peachtree Street, NE, Atlanta
GA 30303
(USA) 1-800-225-6119
The latest Builders Merchant Building Index (BMBI) report shows builders’ merchants’ value sales in October were up +1.2% compared to the same month last year.
Posted in Articles, Bathrooms & Toilets, Bricks & Blocks, Building Associations & Institutes, Building Industry News, Building Products & Structures, Building Services, Building Systems, Civil Engineering, Cladding, Concrete, Cement, Admixtures, Drainage, Drainage Services, Floors, Garden, Hand Tools, Hard Landscaping & Walkways, Health & Safety, Heating Systems, Controls and Management, Heating, Ventilation and Air Conditioning - HVAC, Information Technology, Interior Design & Construction, Interiors, Landscaping, news, Paints, Paints, Coatings & Finishes, Pipes, Pipes & Fittings, Plant, Equipment and Hire, Plumbing, Power Tools, Publications, Research & Materials Testing, Restoration & Refurbishment, Retrofit & Renovation, Site Preparation, Sustainability & Energy Efficiency, Timber Buildings and Timber Products, Walls, Waste Management & RecyclingKids’ Village is delighted to have partnered with GEZE UK as their 2025 charity of the year – find out more via the article…
Posted in Access Control & Door Entry Systems, Architectural Ironmongery, Articles, Building Industry Events, Building Industry News, Building Products & Structures, Building Services, Charity work, Doors, Facility Management & Building Services, Health & Safety, Restoration & Refurbishment, Retrofit & Renovation, Security and Fire Protection, WindowsThe Encon Group, the leading independent distributor of building materials, is pleased to announce that it has been awarded Silver membership of The 5% Club by the 2024/25 Employer Audit Scheme.
Posted in Articles, Awards, Bricks & Blocks, Building Associations & Institutes, Building Industry Events, Building Industry News, Building Products & Structures, Building Regulations & Accreditations, Building Services, Building Systems, Civil Engineering, Cladding, Concrete, Cement, Admixtures, Facades, Hard Landscaping & Walkways, Health & Safety, Insulation, Landscaping, Plant, Equipment and Hire, Recruitment, Restoration & Refurbishment, Retrofit & Renovation, Site Preparation, Training, WallsLocated in Charlton, South London, SWA member West Leigh was established during the Blitz, in 1943. During the destruction in London, the company helped in repairing windows and facades that had been damaged by bombings throughout the city.
Posted in Articles, Building Associations & Institutes, Building Industry News, Building Products & Structures, Building Services, Building Systems, Case Studies, Facades, Glass, Glazing, Restoration & Refurbishment, Retrofit & Renovation, Steel and Structural Frames, Walls, Windows