Assessing pre-contract risk

Reducing risk at the pre-contract stage of a construction project

  • 14 Sep 2017

When​ ​looking​ ​at​ ​risk​ ​managing​ ​a​ ​construction​ ​project,​ ​one​ ​of​ ​the​ ​critical time​ ​periods​ ​that​ ​is​ ​often​ ​overlooked​ ​is​ ​pre-contract​ ​risk: assessing​ ​the company​ ​you’ll​ ​be​ ​working​ ​for​ ​and​ ​with​ ​before​ ​you​ ​invest​ ​any​ ​time​ ​or resources​ ​in​ ​the​ ​project.

One​ ​of​ ​the​ ​greatest​ ​threats​ ​to​ ​a​ ​project​ ​and​ ​one​ ​of​ ​the​ ​biggest​ ​causes​ ​for potential​ ​disputes​ ​is​ ​a​ ​failure​ ​to​ ​properly​ ​understand​ ​the​ ​requirements​ ​of​ ​the contract​ ​and​ ​properly​ ​address​ ​pre​-contract​ ​risk.

There​ ​are​ ​so​ ​many​ ​variables​ ​and​ ​risks​ ​associated​ ​with​ ​being​ ​part​ ​of​ ​a​ ​large scale​ ​project,​ ​possibly​ ​with​ ​third​ ​party​ ​vendors​ ​involved,​ ​regarding​ ​the project,​ ​the​ ​companies​ ​involved,​ ​the​ ​financing​ ​and​ ​financial​ ​institutions involved.​ ​

The​ ​Kenzie​ ​Group​ ​has​ ​put​ ​together​ ​a​ ​brief​ ​guide​ ​to​ ​help​ ​you​ ​to​ ​reduce​ ​pre-contract​ ​risk​ ​in​ ​your​ ​project.​ ​The​ ​guide​ ​prompts​ ​thought​ ​into​ ​some​ ​of​ ​the questions​ ​you​ ​should​ ​be​ ​asking​ ​yourself,​ ​and​ ​the​ ​factors​ ​you​ ​need​ ​to​ ​be considering​ ​before​ ​tendering​ ​on​ ​a​ ​project​ ​or​ ​finalizing​ ​the​ ​project.

Pre-contract risk management

Risk​ ​management​ ​can​ ​start​ ​when​ ​you​ ​have​ ​an​ ​opportunity​ ​to​ ​tender​ ​for​ ​a project.​ ​At​ ​this​ ​stage,​ ​you​ ​need​ ​to​ ​make​ ​the​ ​decision​ ​whether​ ​it’s​ ​worth​ ​your time​ ​to​ ​even​ ​prepare​ ​and​ ​submit​ ​your​ ​tender.

The​ ​key​ ​criteria​ ​to​ ​be​ ​considered​ ​when​ ​deciding​ ​on​ ​whether​ ​you​ ​should submit​ ​your​ ​tender​ ​start​ ​with​ ​identifying​ ​the​ ​risk.​ ​Once​ ​you’ve​ ​identified​ ​the potential​ ​risk​ ​you’ll​ ​need​ ​to​ ​go​ ​through​ ​the​ ​process​ ​of​ ​evaluating​ ​it.​ ​Now, you’re​ ​able​ ​to​ ​mitigate​ ​the​ ​risk​ ​by​ ​deciding​ ​if​ ​you​ ​are​ ​going​ ​to​ ​decline​ ​the tender,​ ​accept​ ​the​ ​risk​ ​but​ ​cost​ ​accordingly​ ​or​ ​identify​ ​a​ ​way​ ​to​ ​reduce​ ​or transfer​ ​the​ ​risk.

For​ ​example,​ ​before​ ​tendering​ ​for​ ​that​ ​great​ ​new​ ​project​ ​ask​ ​yourself​ ​these questions:

  • Is​ ​the​ ​employer​ ​financially​ ​secure?​ ​Do​ ​some​ ​research​ ​on​ ​the​ ​finances​ ​of​ ​the employer​ ​to​ ​determine​ ​if​ ​it’s​ ​worth​ ​your​ ​time​ ​tendering.
  • How​ ​is​ ​the​ ​project​ ​being​ ​funded,​ ​and​ ​is​ ​the​ ​funding​ ​really​ ​secure?​ ​Analyze the​ ​realities​ ​and​ ​cost​ ​of​ ​funding.
  • Does​ ​the​ ​employer​ ​have​ ​a​ ​reputation​ ​for​ ​paying​ ​on​ ​time?​ ​Get​ ​to​ ​know​ ​your future​ ​bedfellow,​ ​you​ ​may​ ​need​ ​to​ ​factor​ ​in​ ​late​ ​payments​ ​into​ ​your​ ​tender.
  • Has​ ​the​ ​employed​ ​signed​ ​the​ ​Fair​ ​Payment​ ​Charter?​ ​It’s​ ​a​ ​quick​ ​check​ ​but worth​ ​knowing​ ​if​ ​you​ ​might​ ​be​ ​working​ ​for.

When​ ​looking​ ​at​ ​risk​ ​managing​ ​this​ ​stage​ ​of​ ​the​ ​process,​ ​you​ ​need​ ​to​ ​bear​ ​in mind​ ​that​ ​it’s​ ​something​ ​that​ ​needs​ ​to​ ​be​ ​revisited​ ​on​ ​a​ ​regular​ ​basis.

Initially,​ ​at​ ​the​ ​expression​ ​of​ ​interest​ ​stage,​ ​then​ ​again​ ​during​ ​the​ ​tender application​ ​stage.​ ​You​ ​need​ ​to​ ​revisit​ ​your​ ​analysis​ ​again​ ​at​ ​contract​ ​issue before​ ​making​ ​the​ ​decision​ ​to​ ​accept​ ​the​ ​contact.

Following​ ​the​ ​recent​ ​administration​ ​of​ ​a​ ​number​ ​of​ ​major​ ​contractors,​ ​in​ ​the current​ ​industry​ ​climate,​ ​it​ ​is​ ​essential​ ​that​ ​you​ ​are​ ​confident​ ​that​ ​your employer,​ ​either​ ​the​ ​main​ ​contractor​ ​or​ ​the​ ​client,​ ​is​ ​able​ ​to​ ​pay​ ​for​ ​the works​ ​you​ ​have​ ​planned​ ​to​ ​carry​ ​out.​ ​Although​ ​this​ ​may​ ​seem​ ​like​ ​common sense,​ ​it​ ​is​ ​paramount​ ​and​ ​should​ ​not​ ​be​ ​ignored.

During​ ​the​ ​tender​ ​and​ ​pre​-​contract​ ​stage,​ ​when​ ​reviewing​ ​the​ ​contract,​ ​it​ ​is important​ ​to​ ​consider​ ​issues​ ​that​ ​may​ ​cause​ ​risks​ ​to​ ​both​ ​the​ ​time​ ​and​ ​cost of​ ​the​ ​project:

  • Is​ ​the​ ​program​ ​realistic​ ​for​ ​the​ ​works​ ​which​ ​have​ ​been​ ​defined? Are​ ​there​ ​contractually​ ​binding​ ​target​ ​or​ ​interim​ ​dates?
  • Are​ ​the​ ​completion​ ​dates​ ​clear​ ​and​ ​unconditional?
  • Do​ ​all​ ​program​ ​revisions​ ​need​ ​to​ ​be​ ​approved?
  • Can​ ​you​ ​claim​ ​extensions​ ​of​ ​time​ ​for​ ​events​ ​outside​ ​of​ ​your​ ​control​ ​which delay​ ​the​ ​works?
  • Can​ ​you​ ​claim​ ​loss​ ​of​ ​productivity​ ​for​ ​events​ ​outside​ ​your​ ​control​ ​which disrupt​ ​the​ ​works?
  • Are​ ​liquidated​ ​damages​ ​(LADs)​ ​set​ ​at​ ​a​ ​reasonable​ ​level?
  • If​ ​the​ ​project​ ​takes​ ​a​ ​long​ ​time,​ ​does​ ​the​ ​contract​ ​permit​ ​price​ ​fluctuations for​ ​rising​ ​costs​ ​in​ ​materials​ ​or​ ​energy?
  • Can​ ​the​ ​employer​ ​ask​ ​you​ ​to​ ​complete​ ​works​ ​sooner​ ​than​ ​the​ ​originally agreed​ ​completion​ ​date?
  • Is​ ​the​ ​retention​ ​per​ ​cent​ ​acceptable? 
  • What​ ​is​ ​the​ ​period​ ​between​ ​certification​ ​of​ ​instalments​ ​and​ ​the​ ​final​ ​date​ ​for payment?​ ​
  • If​ ​you​ ​are​ ​subcontracting​ ​works​ ​out,​ ​does​ ​this​ ​meet​ ​your subcontractor’s​ ​expectations​ ​regarding​ ​payment​ ​periods?
  • Is​ ​the​ ​procedure​ ​for​ ​changing​ ​the​ ​price​ ​due​ ​to​ ​instructions​ ​or​ ​risk​ ​events robust​ ​and​ ​workable?
  • Is​ ​the​ ​percentage​ ​of​ ​the​ ​price​ ​represented​ ​by​ ​provisional​ ​sums​ ​acceptable?
  • Can​ ​the​ ​employer​ ​omit​ ​works​ ​and,​ ​if​ ​so,​ ​how​ ​would​ ​this​ ​affect​ ​your​ ​profit margin?

In summary

Larger​ ​scale​ ​construction​ ​projects​ ​are​ ​complicated​ ​beasts with a ​lot​ ​of​ ​moving parts,​ and ​a​ ​lot​ ​of​ ​parties​ ​involved.​ ​A​ ​company​ ​involved​ ​in​ ​construction​ ​is​ ​going to​ ​have​ ​to​ ​prepare​ ​to​ ​be​ ​exposed​ ​to​ ​an​ ​increasing​ ​amount​ ​of​ ​risk​ ​and​ ​that means​ ​to​ ​have​ ​stringent​ ​risk​ ​management​ ​processes​ ​in​ ​place,​ ​starting​ ​with risk​ ​management​ ​at​ ​the​ ​pre​-contract​ ​stage.

PWC​ ​recently​ ​discovered​ ​that​ ​out​ ​of​ ​the​ ​companies​ ​surveyed,​​ ​71%​ ​firmly held​ ​the​ ​belief​ ​that​ ​they​ ​have​ ​robust​ ​security​ ​activities,​ ​however,​ ​of​ ​that​ ​71%​ ​just​ ​32%​ ​actually​ ​required​ ​their​ ​third​ ​parties​ ​to​ ​comply​ ​with​ ​those policies.

Conducting​ ​some​ ​due​ ​diligence​ ​at​ ​the​ ​pre-contract​ ​stage​ ​allows​ ​you​ ​to​ ​paint are​ ​a​ ​more​ ​accurate​ ​picture​ ​of​ ​the​ ​risks​ ​associated​ ​with​ ​the​ ​project​ ​and​ ​how those​ ​risks​ ​may​ ​or​ ​may​ ​not​ ​be​ ​mitigated.​ ​At​ ​the​ ​same​ ​time,​ ​you​ ​should research​ ​the​ ​companies​ ​associated​ ​with​ ​the​ ​project,​ ​assess​ ​their​ ​risk​ ​as potential​ ​partners

Due​ ​to​ ​the​ ​time​ ​periods​ ​connected​ ​with​ ​such​ ​projects,​ ​circumstances​ ​and risk​ ​can​ ​change​ ​and​ ​needs​ ​to​ ​be​ ​revisited​ ​at​ ​several​ ​key​ ​points​ ​during​ ​the project,​ ​including​ ​some​ ​critical​ ​stages​ ​during​ ​the​ ​pre​-contract​ ​stage.

The​ ​questions​ ​answered​ ​above​ ​should​ ​be​ ​answered​ ​in​ ​as​ ​much​ ​detail​ ​as feasible.​ ​Some​ ​elementary​ ​checks​ ​should​ ​be​ ​conducted​ ​at​ ​the​ ​tender invitation​ ​stage​ ​with​ ​a​ ​more​ ​complete​ ​risk​ ​analysis​ ​completed​ ​during​ ​the tender​ ​application​ ​process​ ​as​ ​naturally,​ ​you​ ​look​ ​at​ ​the​ ​project​ ​under​ ​a microscope.

If​ ​you​ ​are​ ​unsure​ ​of​ ​the​ ​answers​ ​to​ ​any​ ​of​ ​the​ ​above​ ​questions,​ ​then​ ​it​ ​is advisable​ ​to​ ​discuss​ ​with​ ​a​ ​construction​ ​contract​ ​claim​ ​consultant​,​ ​and​ ​the Kenzie​ ​Group​ ​can​ ​help​ ​ensure​ ​your​ ​contract​ ​is​ ​robust​ ​with​ ​a​ ​fair​ ​and appropriate​ ​balance​ ​of​ ​risk,​ ​whilst​ ​reducing​ ​the​ ​risk​ ​for​ ​you​ ​wherever possible.

Leave a Reply

Latest news

LIFTEX

Registration opens for LIFTEX 2025 (11 - 12 June)

Registration has opened for LIFTEX 2025. Now in its 37th year, the show is the UK’s only dedicated exhibition for the lift, escalator and access industry and takes place only once every three years.

Posted in Accessibility, Articles, Building Associations & Institutes, Building Industry Events, Building Industry News, Building Products & Structures, Building Regulations & Accreditations, Building Services, Exhibitions and Conferences, Facility Management & Building Services, Health & Safety, Restoration & Refurbishment, Retrofit & Renovation

Tobermore
Tobermore

Groundworkers - improve your tender success rates with Tobermore's Secura Portal

For groundworkers, tendering residential retaining wall projects can be a time-consuming and complicated process. The key is to tender using Tobermore’s Secura modular concrete block retaining walls rather than the default masonry specification & the Secura Portal, an online tool.

Posted in Articles, Bricks & Blocks, Building Industry News, Building Products & Structures, Building Services, Building Systems, Case Studies, Civil Engineering, Concrete, Cement, Admixtures, Facility Management & Building Services, Hard Landscaping & Walkways, Information Technology, Innovations & New Products, Landscaping, Posts, Restoration & Refurbishment, Retrofit & Renovation, Walls

Abloy