Section 4.2 is the section of the Technical Handbook building regulations in Scotland that refers to the accessibility and use of buildings. Section 4.2 lists the mandatory standards that must be adhered to in the process of ensuring your building is fully accessible to all building users. It provides rules around fulfilling the requirements of providing access to a building, within a building and between storeys.
Section 4.2 is only applicable in Scotland, Part M is the English equivalent.
Section 4.2 covers the mandatory standards that must be adhered to in the process of ensuring your building is fully accessible to all building users, either when planning a new building or when adapting an existing one, advising that vertical circulation should suit both the building and the people who’ll be using it.
Circulation within buildings should allow all building users, including those who require disabled access to move freely and without difficulty at all times. This can be considered and achieved at the building design stage in accordance with British Standards BS 8300 – Design of buildings and their approaches to meet the needs of disabled people code of practice, however there are exceptions to the rule.
Exceptions include building refurbishments and conversions. When converting a building, the requirements are to meet the standard ‘so far as is reasonably practicable’, with access being no worse than before (Regulation 12, schedule 6 in the Technical Handbook).
Although the requirements will obviously vary considerably depending on the type of lift you are installing and the building type in which you are installing it, there are some general requirements that apply.
Firstly that you carefully consider whether the type of lift you’re planning to install is ‘fit for purpose’ and that ‘a building should be accessible to everyone, whilst recognising that ‘it may not be necessary or, in some cases, reasonably practicable to provide full access to all parts of a building.’
Every building must be designed and constructed in such a way that:
for non-domestic buildings, safe, unassisted and convenient means of access is provided throughout the building
in residential buildings, a proportion of the bedrooms must be accessible to a wheelchair user
in domestic buildings, safe and convenient means of access is provided within common areas and to each dwelling
for dwellings, safe and convenient means of access is provided throughout the dwelling
in dwellings, unassisted means of access is provided to, and throughout, at least one level.
Exceptions noted include limited access, e.g. stepped access (in a residential building such as a hotel, to accommodation unsuitable for a disabled user) or (a raised area in a public building where an equivalent service is available on a lower level) – see Standard 4.10.
Typically in non-domestic buildings with two or more floors, this means is a passenger lift first and foremost and a platform lift if it is not possible due to building or usage limitations. For smaller distances, a platform lift can be the first choice.
For both passenger and platform lifts any lifting device should be designed and installed to include the following general provisions:
– a clear landing at least 1.5m x 1.5m in front of any lift entrance door
– tactile controls on each level between 900-1100mm above the landing, within the lift car on a side wall between 900-1100mm, above the car floor and at least 400mm from any corner
– lift doors, handrails and controls contrast visually with surrounding surfaces
– landing signalling system that gives notification of the lift
– two-way communication, operable by a person with a hearing impairment, that allows contact with the lift if an alarm is activated, along with a visual alarm indicator.
Generally, unassisted access between storeys should be provided by a passenger lift, with the installation meeting the recommendations of BS EN 81-70: 2003. However in some circumstances, when altering existing buildings or within new buildings with a small storey area, it may not always be reasonably practicable to install a passenger lift which is where an enclosed platform lift can play its part.
In addition to general provisions for lifting devices, a passenger lift should be provided with:
Where it’s not possible or practical to place a passenger lift an enclosed platform lift is a suitable alternative. Like passenger lifts, there are additional recommendations for disabled access lifts.
In addition to general provisions for lifting devices, a powered lifting platform, or platform lift should (if serving a storey to which the public have access) have a platform size of 1100mm wide by 1400mm deep and a clear opening width to any door of 850mm, or if serving any other storey, have a platform size of at least 1050mm wide by 1250mm deep and a clear opening width to any door of 800mm.
They should also be:
– fully contained within an enclosure with a speed of no more than 0.15 metres per second
– have a horizontal handrail, 900mm above the floor on at least one side of the platform
– provided with permanent and clear operating instructions adjacent to or within the platform
Whilst the regulations state platform lifts should be operated by “continuous pressure control, of a form operable by a person with limited manual dexterity” there are one-touch operation alternatives, like our Midilift Plus cabin platform lift range, enabling much easier operation.
In such cases, where vertical travel is not more than 4.0m, the installation of a powered lifting platform, will be meeting the recommendations of BS 6440: 1999 may be considered, such as our Lowriser wheelchair platform steplift range.
Most of the requirements of Section 4.2 are identical to Part M . However the platform size requirements do differ with the Scotland document, requiring larger minimum sizes for both low and medium-rise platform lifts. There are also some additional recommendations surrounding lifts in buildings, namely the Equality Act, BS8300 design guidance which can be found in our blog – Building Regulations – Do I need a lift.
Any of our platform and passenger lifts can adhere to the Section 4.2 requirements and our expert team are always on hand to provide you with a lifting product that is not only compliant to the relevant standards and regulations but also blends effortlessly into your building aesthetics.
A reputable lift provider will be able to assist you in your decision making, however, it’s certainly worth being well-informed about these design considerations yourself. Here at Stannah, we offer a broad range of products to enable easy vertical circulation, working with you to solve your access problem and comply with building regulations.
English Spirit Distillery has used an extensive package of Altro products front and back of house, in their new visitor centre café, shop and viewing area for the working distillery.
Posted in Articles, Bathrooms, Bedrooms & Washrooms, Building Industry News, Building Products & Structures, Building Systems, Case Studies, Floors, Interior Design & Construction, Interiors, Kitchens, Restoration & Refurbishment, Retrofit & Renovation, Timber Buildings and Timber Products, WallsAbloy UK has supplied The Safety Letterbox Company Ltd with a bespoke Sentry CL811 Camlock for use in its Secure Information Boxes, assisting life safety and complying with new regulations and legislation for high rise buildings.
Posted in Access Control & Door Entry Systems, Architectural Ironmongery, Articles, Building Industry News, Building Products & Structures, Building Regulations & Accreditations, Building Services, Case Studies, Facility Management & Building Services, Health & Safety, Posts, Restoration & Refurbishment, Retrofit & Renovation, Security and Fire ProtectionSituated at the northern edge of a newly developed retail park near Bristol, the Abbey Wood Travelodge was conceived as part of the company’s new Budget-Luxe line of hotels – it features CUPACLAD, from CUPA PIZARRAS.
Posted in Articles, Building Industry News, Building Products & Structures, Building Systems, Case Studies, Cladding, Concrete, Cement, Admixtures, Facades, Posts, Restoration & Refurbishment, Retrofit & Renovation, WallsOrigin’s latest investment is set to redefine industry standards as it launches its own in-house powder coating facility.
Posted in Aluminium Products, Articles, Building Industry News, Building Products & Structures, Building Systems, Doors, Glass, Glazing, Innovations & New Products, Paints, Coatings & Finishes, Restoration & Refurbishment, Retrofit & Renovation, Site Preparation, Windows