Stockton Globe – Delta case study on sympathetic waterproofing solutions

  • 4 Nov 2020

Work to refurbish Stockton’s Globe Theatre began in 2011, but the renovation has been dogged by structural issues, including the discovery of unsupported walls, rotting timbers and a weak roof – Delta’s Technical Team, along with Delta Registered Installers Marsden Damp Services, were approached by the main contractor Wilmott Dixon to give assistance on designing a robust waterproofing solution.

Working in collaboration with the architects and project team, this team of waterproofing experts were easily able to offer a simplistic and practical approach.

Methodology

The project was split into two waterproofing phases, with Phase 1 focusing on the existing stage and orchestra pit and Phase 2 on the seating and ancillary rooms, which all required the installation of a Type C waterproofing system to ensure a Grade 3 habitable environment was created.

As Type C waterproofing systems are the most reliable and maintainable approach to the project were incorporated into the BS8102:2009 structural waterproof design.

Before installation of the Delta Type C membranes, all existing walls and the new concrete slab were treated with Koster Polysil TG 500 anti-lime inhibiter to seal the surfaces and reduce the leaching of ‘free lime’ which could cause blockages behind the membranes. 

The principles of a Delta Type C cavity drainage system are to allow moisture or running water to travel behind the membrane within a controlled channelled drainage system.

Any water ingress is collected and discharged via a suitable sump pump. To ensure the Type C system was fully maintainable, inspection ports were located at every major change of direction.

All floors and drainage elements were tested to ensure these would drain as the system was designed and BS 8102:2009 requirements were met.

Delta MS500 and PT mesh membrane 8mm cavity drain membranes were used for the waterproofing of the walls. The Delta MS500 was fixed using Delta Qwik-seal plugs, fixed at 600mm centres with added benefits of Delta double-sided butyl tape to seal joints and overlaps. Delta butyl Corner strip tape was added to seal wall/floor joints. 

Delta MS20 20mm cavity drain membrane was used for waterproofing the floors. This is a heavy gauge version and incorporates 20 mm studs which offer extra drainage capacity.

Delta MS20 was used as a ‘cavity former’ for this type of new construction. The Delta MS20 is neatly rolled out across the basement floor; the sheets are overlapped and sealed in accordance with the manufacturer’s instructions.  Corner strip tape was added to seal wall/floor joints.

Case Study Results

Stockton’s Globe Theatre has been transformed from an unused derelict building back to its former glory for many theatrical and musical performances to be enjoyed once again.

By incorporating a Delta System, the theatre is completely protected against water ingress along with Delta’s tested product life cycle and installation by Delta Registered Installers that the project easily complied to British Standards.

Delta Membrane Systems,
Delta House,
Merlin Way,
North Weald,
Epping,
Essex,
CM16 6HR
United Kingdom

Visit Delta Membrane Systems' website

Leave a Reply

Latest news

Senior pledges to ‘bee’ part of the solution with new biodiversity initiative

Senior Architectural Systems has installed its first on-site beehive, marking another step forward in its commitment to sustainability and biodiversity.

Posted in Articles, Building Industry News, Building Products & Structures, Building Services, Curtain Walling, Doors, Glass, Glazing, Innovations & New Products, news, Restoration & Refurbishment, Retrofit & Renovation, Sustainability & Energy Efficiency, Walls, Windows

West Fraser range delivering key benefits for South-East carpentry company

An experienced carpenter and building site manager who has recently set up his own company is using high performance panel products from the West Fraser range.

Posted in Articles, Building Industry News, Building Products & Structures, Building Systems, Case Studies, Garden, Restoration & Refurbishment, Retrofit & Renovation, Sustainability & Energy Efficiency, Timber Buildings and Timber Products

WindowBASE launches new prospect databases at FIT Show

Visit WindowBASE at the FIT Show to see first-hand how it helps companies find new customers – the company is launching an easy-to-use, intuitive platform on Stand G16 at the NEC Birmingham from 29th April – 1st May.

Posted in Articles, Building Industry Events, Building Industry News, Building Products & Structures, Building Services, Doors, Exhibitions and Conferences, Glass, Glazing, Information Technology, Innovations & New Products, Posts, Publications, Research & Materials Testing, Restoration & Refurbishment, Retrofit & Renovation, Windows